INSPECTION POINT
| Contractor |
Sub-Contractor |
REMARKS | ||
Site Eng | QC | ||||
1 | Inspection is as per the approved Shop Drawings. |
|
|
|
|
2 | Materials used are as per approved Material Submittal |
|
|
|
|
3 | Space of supports are as per the specifications, approved shop drawing |
|
|
|
|
4 | Sleeves are provided wherever Pipe crosses walls and slabs |
|
|
|
|
5 | Coordination with other trades is taken cared of avoiding unnecessary clashes |
|
|
|
|
6 | Threaded rods used as supports have correct sizes, cut ends galvanize painted and cut with sufficient length |
|
|
|
|
7 | Supports used are independent from other trades, no sharing of supports |
|
|
|
|
8 | Applicable accessories, fittings are installed |
|
|
|
|
9 | Approved Labeling materials are provided |
|
|
|
|
10 | Installation is clean, free from cement debris and unnecessary objects. |
|
|
|
|
COMMENTS: | |||||
| |||||
| |||||
| |||||
| |||||
| |||||
|
SUB-CONTRACTOR | Contractor | Remarks | ||
SITE ENGINEER | QUALITY ENGINEER | |||
Name: | ||||
Signature: |